drinking water servicesprivate treatment
 

Drinking Water Services
Rocfort Road
Snodland
Kent ME6 5AH
0845 3454 213

email:

Water Audit Case Studys

University of Kent , Canterbury :

Pump Regimes

University of Kent at Canterbury The supply regime created recurring bursts on the distribution network as pumps operated on a simple reservoir level drop control mechanism. The violence of the start up caused pressure surges in the mains giving rise to regular leaks.

Re-modelling the control regime and changing the pump sets allowed for a much slower start up. This along with continuous flow and pressure monitoring at the revenue meters gave reliable nightline profiles that were then used as the basis of focus for baseline reduction.

Consumption savings equivalent to £21k per annum have been achieved for a modest investment of £8k. Rationalisation of the distribution network has optimised the fire fighting facilities and reduced the number of ‘dead legs’ thus reducing the risk of Legionellosis and other bacteriological growth. This is a particularly highly important requirement for this particular customer.

 

MoD Deepcut Barracks:

Infrastructure Revision and Leak Repairs

Following an initial desk top study to determine the relationship between occupancy and consumption, this barracks site indicated very high potential loses and wastage. Logging the main revenue meter ascertained a nightline of 25m 3 per hour. Further sub metering and logging of flows and pressures indicated loses associated with three discreet areas; housing, the water tower and medical block.

Standard leakage detection practices including acoustic logging and correlation located single leaks in two of the areas. Repairs and infrastructure revision surrounding the water tower caused a nightline reduction of 10m 3 per hour, equating to a saving of £90k per annum.

Significant additional verification activity was necessary to prove that the medical block had multiple supply leaks, one of which was under the centre of the building. Many water regulations contraventions also proved necessary to rectify and on completion the nightline dropped further to 7m 3 per hour, which is an additional 71k per annum saving.

These forward savings have been achieved for a total investment of less then £15k giving a pay back period of less than 2 months.

William Harvey Hospital :

Internal Over Flow

William Harvey Hospital, Ashford A major acute hospital covering a population of 75k in the south east of Kent .

Continuous consumption logging showed an increase in nightline by 3 m 3 per hour from the standard profile. Our Water Audit team quickly narrowed the problem down to an area associated to the supply to the hospital laundry, located in a multi story block.

The main feed supplied a header tank with inoperative float control allowing water to cascade down an internal overflow and return straight to the foul drainage system. Simple rectification of this control mechanism gave rise to a £3.5k per month saving on water bills to the East Kent NHS trust.

National Grid (power converter station):

Leak detection and PRV

As a result of recurring poor pressure Water Audit were invited to undertake a study of the supply regime and advise on improvements in water efficiency for the site.

Various problems were found surrounding the fire main which had a pressurised system operating continuously. This suggested down stream leakage as the operation was pressure controlled. Additionally, two leaks were found, under 415,000 volt transformers, on poorly installed black polyethylene supply pipes. The rectification of these leaks was undertaken by specialist contractors due to the nature and sensitivity of the works.

In order to protect this particularly sensitive infrastructure a Pressure Reducing Valve (PRV) was installed at the commencement of the supply. The outlet pressure set to 2.5 bar representing a reduction from 4 bar. This along with the supply repairs reduced the nightline by 4 m 3 per hour, a saving of £54k per annum.

A further benefit of the PRV installation was to increase the immediate network area pressure, reducing the number of low pressure complaint calls from Mid Kent Water customers in the area.

For Further information on water quality click here:

 

 

 

 

 

Water is one of our biggest overheads and it is essential to the success of our business

 

 

 

 

 

 

 

There is a mixture of cast iron, steel and plastic pipes,

both the older black pipes and the more modern blue

 

 

 

 

 

 

 

 

 


Links:

The Street Works (Reinstatement) Regulations 1992
  Department for Transport - Street Works
  Kent CC Roadworks Database